Lake Wilmore Multi-Purpose Fields

Development Services Building
171 N Ross St
-
(334) 501-7390 -
webengineering@auburnalabama.org -
- M-F
- 7:30AM-4:30PM
-
\t\t\t\t{{SocialMediaLinks}} \t\t\t \t\t
Project Overview New Facilities Renovations or Improvements
This project consists of construction of four multi-purpose synthetic turf fields sized to accommodate football and lacrosse games and practice as well as baseball/softball practice, as well as six covered lit pickleball courts in addition to the twelve courts constructed with the Lake Wilmore Community Center project. Project scope includes fields, LED field lighting, restroom/concessions/storage building, parking and a playground for children ages 5-12. The project is part of the City of Auburn's Parks‚ Recreation‚ & Culture Master Plan.
Please note that project completion dates are subject to change based on weather and other conditions. Project anticipated finish dates may not coincide with actual day of opening.
Opening: An official facility opening date for the public will be coordinated by the contractor and City staff, and will be announced at a later date.
Status
- Design
- Bid Advertisement
- Contracts
- Construction
40%
The additional pickleball ball courts have been poured and the freestanding wall in front of the playground is complete. The contractor is working to remove the remaining rock for the electrical lines and the field drainage pipe, and next steps include placing the base for the parking lot and the stone layer for the fields.
Photos




Timeline
Construction Finishes
Aug 15, 2025
Close Out Finishes
Jul 2, 2025
Close Out Starts
Jun 3, 2025
Contracts Finishes
Jun 3, 2024
Construction Starts
Jun 3, 2024
City Council / AWWB Starts
Apr 16, 2024
Contracts Starts
Apr 16, 2024
Bid Advertisement Finishes
Apr 9, 2024
Bid Opening Starts
Apr 9, 2024
Bid Advertisement Starts
Mar 17, 2024
Design Finishes
Jan 19, 2024
Design Starts
Oct 1, 2022